19.15m x 6.25m x 6m @ 120 Tonnes.

In May 2013 Leicester Heavy Haulage were asked to provide a quotation for transporting a 120 Tonne Metering Skid to the nearest port from the manufacturer.

Upon acceptance of our official quotation the company carried out a Route Survey and prepared a detailed report for the client highlighting the challenges in moving the Skid to the chosen docks.  The report also detailed the solutions that Leicester Heavy Haulage would provide to ensure safe delivery of the Skid.

IMG_4387

Due to the overall loaded height of the Skid and Scheuerle Modular Flatcombi Trailer being 6.85m it was necessary to identify a High Load Route for the movement to avoid all overhead obstructions (e.g motorway bridges).

A Special Order Permit from the Highways Agency was arranged due to the width exceeding 6.1m and the overall Gross Vehicle Weight being over 150 Tonnes.

IMG_4403

The movement of the Metering Skid took place following completion of construction in February 2014.

The load needed Police Escorts throughout the entire journey and travelled on a Sunday morning to reduce congestion.

Several items of Street Furniture were also required to be removed due to the overall length of the vehicle and trailer combination and the width of the cargo.

IMG_4401

Leicester Heavy Haulage arranged BT Openreach Escorts and Western Power were also in attendance to lift overhanging cables over the top of the Metering Skid.

IMG_4514

After delivery to the docks the Skid was offloaded into a Coaster Vessel using a 1200 Tonne Mobile Crane  in order for it to be moved to Antwerp for a direct lift into a Vessel for onward shipment to Korea.